COPY
FCGM-581100
AFCGM
21 February 1958
MEMORANDUM FOR DIRECTOR OF GUIDED MISSILES, OSD
SUBJECT: ICBM Force Objectives
References: a. SAFS Memo, 10 Feb 58
b. SAFS
Memo, 17 Feb 58
c. AFCGM
Memo, 21 Feb 58
1. This memorandum is in response to a verbal request from your office to specify the Air Force ICBM planning objectives with program costs.
2. In arriving at the force objective mix for FY 63 and 64 the following factors have been considered:
a. The recommendations of the Gaither Committee that a force of 600 ICBMs is required.
b. The strategic target requirement.
c. The requirement to maintain a strong offensive posture continuously and therefore not divert unduly large sums of money and manpower from the manned bomber force to the strategic missile system until prospects of achieving reliability and accuracy performance requirements for missiles are assured.
d. The fact that first generation of ICBMs, ATLAS and TITAN are expensive and complex. Expectations are that replacement of the first generation by a simpler, less expensive solid propelled ICBM (MINUTEMAN) will begin in 1963.
e. The United States as a nation will probably be well into the space age by 1963/65. Any ATLAS and TITAN boosters which are excess to operational force needs during this time period will be employed in astronautics programs.
3. After consideration of the above factors, the Air Force recommends approval of the following ICBM force structure. Upon receipt of approval, funding estimates will be refined and a financial plan will be submitted. The number of missiles is a firm requirement. The force mix is subject to change as research and development on ATLAS, TITAN, MINUTEMAN and THORIC progresses.
WD-58-01227
- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -
ICBM FORCE OBJECTIVES
(in numbers of
missiles)
|
FY 58 |
FY 59 |
FY 60 |
FY 61 |
FY 62 |
FY 63 |
FY 64 |
ATLAS |
|
10 |
30 |
70 |
90 |
90 |
90 |
TITAN |
|
|
|
10 |
50 |
110 |
110 |
MINUTEMAN |
|
|
|
|
|
100 |
400 |
Totals |
|
10 |
30 |
80 |
140 |
300 |
600 |
ESTIMATED DOLLAR REQUIREMENTS
(in millions
of dollars)
|
FY 58 |
FY 59 |
FY 60 |
FY 61 |
FY 62 |
FY 63 |
FY 64 |
ATLAS |
653.7 |
665.4 |
588.8 |
443.1 |
142.0 |
107.0 |
72.0 |
Titan |
356.4 |
560.5 |
636.7 |
821.0 |
316.0 |
421.0 |
133.0 |
MINUTEMAN |
26.0 |
233.0 |
276.0 |
308.0 |
290.0 |
240.0 |
185.0 |
Totals |
1036.1 |
1458.9 |
1501.5 |
1572.1 |
748.0 |
768.0 |
390.0 |
PRESENT FUNDING AUGMENTATION REQUIRED
(FY 58 and FY 59)
|
FY 1958 |
FY 1959 |
||
|
Present |
Augmentation |
Present |
Augmentation |
ATLAS |
653.7 |
0 |
665.4 |
0 |
TITAN |
356.4 |
0 |
404.5 |
156.0 |
MINUTEMAN |
0 |
26.0 |
0 |
233.0 |
TOTALS |
1010.1 |
26.0 |
1069.9 |
389.0 |
CHARLES M. McCORKLE
Brigadier General, USAF
Assistant Chief
of Staff
for Guided Missiles
WD-58-01227